SnaplinePOC

Takeoff

Quantities read off the drawings. Everything downstream — the quote, the progress claim, the crew's pay — is computed from this table and nothing else.

Run a takeoff on a new set

Upload the architectural PDF. Claude reads the partition plans, the wall type legend, and the finish schedule, and returns quantities per area.

Board
920 sheets
4x12 5/8" Type X
Board area
44,160 sq ft
Tape
6,900 lf
Joints and corners
Needs review
2 areas
Model confidence under 75%

Riverbend_Ph2_Architectural_IFC.pdf

18 pages · claude-opus-5 · 2026-08-06, 8:56:19 p.m.

Reviewed by estimator
AreaFinishSheetsBoard sq ftTape lfCeiling sq ftConfidence
L1 — Clinic corridors & exam rooms
P1 — 1 layer 5/8" Type X ea. side, 92mm stud
A2.01 partition plan, room tags 101–124, dimension strings on north/south grid. Wall height 3050mm to u/s ceiling per A5.02.
Level 4
Level 4 — flat paint / light texture
41219,7763,0902,10088%
L1 — Imaging suite (lead-lined)
P4 — 5/8" Type X + lead sheet, 1 layer ea. side
A2.01 rooms 130–133. Lead thickness not called out on the partition legend — carried as standard board for quantity, flagged as unresolved.
Level 4
Level 4 — flat paint / light texture
964,60872048061%
L1 — Mechanical & plenum (concealed)
P5 — 1 layer 5/8" Type X, one side, to deck
A2.01 rooms M1–M4, partitions run to u/s deck per section 3/A5.02. Fire taping only — concealed above ceiling.
Level 1
Level 1 — fire taping, concealed
602,88045072%
L2 — Admin offices
P1 — 1 layer 5/8" Type X ea. side, 92mm stud
A2.02 partition plan, offices 201–219, scale 1:100 confirmed against the scale bar.
Level 4
Level 4 — flat paint / light texture
26812,8642,0101,64090%
L2 — Boardroom & reception
P2 — 2 layers 5/8" Type X one side, acoustic
A2.02 rooms 220–221. Finish schedule A9.01 calls Level 5 for reception — raking light off the curtain wall.
Level 5
Level 5 — gloss / critical lighting
844,03263072079%
Total92044,1606,9004,940

What the model assumed, and what it couldn't resolve

An estimator checks the assumptions before the arithmetic

Demo takeoff. Reviewed and accepted by estimator; imaging suite lead thickness still outstanding with the architect.